Photos are a combination of this morning when the PD guys were onsite nice and early and what they had got done over the day, solid effort by the crew.
Morning >>
Afternoon >>.
Showing posts with label Pre Slab. Show all posts
Showing posts with label Pre Slab. Show all posts
Tuesday, 10 January 2012
Monday, 9 January 2012
Back to Work for PD (Day 41)
Noticed that there had been some deliveries onsite and some new trenches dug as my revised slab pour is scheduled for tomorrow (Tuesday 10/01) as advised by my SS last week instead of today (09/01) but some how I doubt all the pre work will get done and it will get rescheduled for a 4th time.
So now expecting/guessing it around Thursday (12/01) this week.(See POST 08/12/2011)
So now expecting/guessing it around Thursday (12/01) this week.(See POST 08/12/2011)
Subscribe to: