Monday 27 February 2012

Bricking Nearly Complete (Day 92)

90% of bricking now complete, mainly left is the fiddly stuff such as round the windows plus the garage once the scafolding comes down around that section.
They have also started to do a bit more roughing in for electrical, rangehoods, etc plus we have a front builders "door". 



Wednesday 22 February 2012

Still Bricking (Day 86)

Checked onsite today and upstairs windows now in along with wrapping.
Expect bricking to recommence tomorrow.






Thursday 16 February 2012

Bricking (Half way there) Day 81

Friday update
Bricking continues focusing on garage & pillars







Monday 13 February 2012

Bricking Basically Complete Ground Floor (Day 77)

Awaiting top floor windows and wrapping to be done so bricking can continue.
Bricks looking good.



Wednesday 8 February 2012

Bricking Continues (Day 72)

Guys making great progress and we are starting to get a feel how it will look.







Monday 6 February 2012

Bricking commenced (Day 71)

Been waiting to see these bricks as they have been delayed since their initial release date of November 1st, 2011.
Happy with how our choice being the "Kooyong" how it is looking at present.





Wednesday 1 February 2012

Roof (Day 65)

Being away and in that time PD have finished framing (well they have sent me the bill!) and finished the roof, plus installed some of the windows and done the guttering.
Wondered about the yellow hose in the bottom two photos, guessing it is for the air compressor for the nail gun top floor? Happy for corrections.