Sunday 29 April 2012

Locked Out (Day 155)

Been away interstate so I was told both painting and tiling was currently being performed, as the house is at lock up and not able to organise a view time had a walk round the block peering in the windows.
Can see lots of small items requiring rectification and lots of pools of water around the block.
Can see internal painting has progressed along with some shelves installed.
Front - south
Side - West

Front yard - very wet

Waiting on finalisation of retaining wall next to garage and connection of downpipe to resolve pools of water lying around
Garage - including pools of water

Laundry - note cupboard on left now has shelves installed
Looking toward galley
Galley - shelves not requested above
Awaiting infill above door
Awaiting fill in expansion joint
Familiy room - hard to pick walls have been painted but they have photos do not do justice

Awaiting infill above doors

Awaiting infill above doors
Awaiting infill above doors
Lots of water lying around garage floor

Half wall between dining room and lounge
Kitchen, awaiting resolution of fridge cavity issue

Kitchen benches
Awaiting staining of study windows - east side
Marks and slight wood damage on study windows south side
 Scalfolding left on block next door still to be picked up, rest went a couple of weeks ago.
Paiting still to be completed under balcony at front

Telstra junction box installed

Wires for fuse box to be located inside garage.




No comments:

Post a Comment