Monday, 5 March 2012

Inspection (Day 99)

Had our independent Pre Plaster inspection and by the look of it PD has also done there framing inspection. As a number of sections contain bright paint & comments.
It would appear some of the issues have been caused when the actual roof scalfolding was installed knocking out some of the roof bracing (trimmers) and chipping a few brick tops.
Another issue which I gather is quite common is the excess bricky mortar running down the inside walls as this will affect the affective draining of moisure if not rectified..
We have also now had most of the heating and cooling system ducting installed.
Hopefully by the end of the month we have all issues resolved from the above 2 reports, bricking completed and cleaned. Eaves and spouting done and plaster installed.
Still think we are about 4 months of a finish date.....