Saturday, 31 December 2011

Xmas Day Aftermath

Checked the block after the Xmas day storms and noticed some of the storm water pipes had come up as well as parts of the block had washed away.
These shots are 5 days later
Not sure what impact on the site will wait for PD to come back in the New year to advise.
Compared to some areas such as Eltham and Taylors Lakes got off light. We were in next suburb to our block and recieved a fair amount of rain & small hail stones.






Friday, 23 December 2011

Progress to Xmas (Day 24)

Credit to PD they have made good progress these last few weeks of 2011 and I'm feeling confident the slab will be laid first 2 weeks of 2012.



Wednesday, 21 December 2011

We are Under Way!!! (Day 22)

PD have commenced as per their updated promise this past week.
We now have the following:-

1. Site cut
2. Retaining wall
3. Site fence
4. Power to site
5. Toilet
6. Lots of holes
7. A happy customer

Thursday, 8 December 2011

Expectations Realigned

Yesterday was given site cut 12/12 today it is now 16/12?
Yesterday was given 22/12 for slab today it is 09/01?

A tap plus three drill holes is all we have to show ONSITE after nearly 5 months of interactions and contract signing back in August 2011.