Checked the block after the Xmas day storms and noticed some of the storm water pipes had come up as well as parts of the block had washed away.
These shots are 5 days later
Not sure what impact on the site will wait for PD to come back in the New year to advise.
Compared to some areas such as Eltham and Taylors Lakes got off light. We were in next suburb to our block and recieved a fair amount of rain & small hail stones.
Saturday, 31 December 2011
Friday, 23 December 2011
Progress to Xmas (Day 24)
Credit to PD they have made good progress these last few weeks of 2011 and I'm feeling confident the slab will be laid first 2 weeks of 2012.
Wednesday, 21 December 2011
We are Under Way!!! (Day 22)
PD have commenced as per their updated promise this past week.
We now have the following:-
1. Site cut
2. Retaining wall
3. Site fence
4. Power to site
5. Toilet
6. Lots of holes
7. A happy customer
We now have the following:-
1. Site cut
2. Retaining wall
3. Site fence
4. Power to site
5. Toilet
6. Lots of holes
7. A happy customer
Thursday, 8 December 2011
Expectations Realigned
Yesterday was given site cut 12/12 today it is now 16/12?
Yesterday was given 22/12 for slab today it is 09/01?
A tap plus three drill holes is all we have to show ONSITE after nearly 5 months of interactions and contract signing back in August 2011.
Yesterday was given 22/12 for slab today it is 09/01?
A tap plus three drill holes is all we have to show ONSITE after nearly 5 months of interactions and contract signing back in August 2011.
Monday, 21 November 2011
Site Start
Any advice b4 our final meeting b4 site start next week?
Rob & Karen
Rob & Karen
Paid for soil test & site survey June 28, 2011
Site Survey July 28, 2011
Soil test August 3, 2011
Promised Start Date OCTOBER 2011
Promised Start Date OCTOBER 2011
New start date November 2011
Start date
We have a confirmed start date after months of waiting.
It will be either Monday 28th, Tuesday 29th or Wdnesday 30th November.
It will be either Monday 28th, Tuesday 29th or Wdnesday 30th November.
Thursday, 11 August 2011
Hi Guys,
We are about to start the process of building a Waldorf 48 with our tender date coming up shortly, so interested in any thoughts & gotcha's as the initial phase of getting a soil and site survey has taken a while longer than I would have expected to even get to the starting gate as we have signed on the basis we start building in October.
Started subscribing to all the blogs out there to educate us from our fellow Waldorf builders.
Rob & Karen
We are about to start the process of building a Waldorf 48 with our tender date coming up shortly, so interested in any thoughts & gotcha's as the initial phase of getting a soil and site survey has taken a while longer than I would have expected to even get to the starting gate as we have signed on the basis we start building in October.
Started subscribing to all the blogs out there to educate us from our fellow Waldorf builders.
Rob & Karen
Paid for soil test & site survey June 28, 2011
Site Survey July 28, 2011
Soil test August 3, 2011
Promised Start Date OCTOBER 2011
Promised Start Date OCTOBER 2011